[1. CALL TO ORDER]

[00:00:07]

I HAVE 530, SO I WILL CALL THIS MEETING OF THE NORTH LAKE PLANNING AND ZONING COMMISSION

[ 2.A. Briefing - Approved Plats Report ]

TO ORDER, PLEASE. FIRST, WE WILL HAVE A BRIEFING ON THE APPROVED PLANS. RIGHT. WE HAVE THREE PLASTER REPORT ON HAVE BEEN APPROVED SINCE OUR YOUR LAST MEETING. A COUPLE OF MINOR PLATS. JUST ONE LOT PLATS AND THEN A PHASE OF PECAN SQUARE. FIRST, THIS IS THE VENDOR EDITION NUMBER FOR MINOR PLAT. THIS IS IN THE NORTHWEST REGIONAL AIRPORT AREA IN THE ETJ JUST IT'S OFF OF EDNA STREET WEST OF THAT AIRPORT AREA. IT'S JUST UNDER AN ACRE SITE AND IT'S BEING PLATTED. IT'S AN EXISTING TRACK OF LAND BEING PLATTED SO THEY CAN GET PERMITS THROUGH THE COUNTY. NO TOWN SERVICES OR PROPOSED WATER SERVICE IS TO BE PROVIDED BY SOUTHWEST WATER SERVICE IN THAT AREA, AND SEWER WILL BE PROVIDED BY SEPTIC SYSTEM. NEXT IS PECAN SQUARE PHASE SIX. THIS IS THE FINAL RESIDENTIAL PHASE OF PECAN SQUARE TO BE PLATTED.

THIS INCLUDES MANY OF THOSE ESTATE LOTS, THE LARGEST LOTS. AND IN THE DEVELOPMENT. SO THERE'S 20 RESIDENTIAL LOTS OVERALL IN. THIS INCLUDES SOME THAT BACK UP TO THE THE HIGHLANDS ON THE FAR WEST SIDE OF THE PECAN SQUARE DEVELOPMENT. SURE. OKAY. PLOT SIX, PHASE SIX.

YES. SO THIS SEEMS LIKE A VERY LARGE AREA TO BE AUTO NOT AUTO APPROVED, BUT NOT GO THROUGH PNC. IS THAT BECAUSE OF THE TOWN'S ORIGINAL AGREEMENT WITH PECAN SQUARE OR. THIS JUST SEEMS LIKE A REALLY LARGE AREA NOT TO GO THROUGH THIS COMMITTEE. PLATS, REGARDLESS OF SIZE, CAN BE APPROVED BY STAFF AS LONG AS THEY MEET ALL ZONING REQUIREMENTS AND ALL PLANNING REQUIREMENTS. AND THAT'S THAT'S THE CASE FOR THIS ONE. SO THE ZONING WAS APPROVED BY THE TOWN.

THERE WAS A DEVELOPMENT AGREEMENT AND THIS COMPLIES WITH THAT. SO ANOTHER THING TO POINT OUT THE BULK OF THIS AREA IS OPEN SPACE. A LOT OF FLOODPLAIN THAT RUNS THROUGH HERE. SO IT'S A 64 ACRES OVERALL BUT JUST 20 RESIDENTIAL LOTS OVER THAT. THANK YOU. THEN FINALLY THIS IS ANOTHER MINOR PLAT IN THE AIRPORT AREA OFF OF COCKLEBURR ROAD. IT'S ALSO A SITE IN THE ETJ, JUST OVER A HALF ACRE. THIS WAS AN EXISTING TRACT BEING PLATTED SO THEY CAN OBTAIN PERMITS THROUGH DENTON COUNTY. SIMILARLY, IT'S BEING PROVIDED WITH WATER FROM SOUTHWEST WATER AND WILL BE SERVED BY A SEPTIC SYSTEM. ON THE TOWN COUNCIL. SURE. SO IT'S

[ 2.B. Briefing - Town Council actions on Planning & Zoning Commission items ]

YOUR LAST MEETING YOU CONSIDER A SITE PLAN FOR CLASSIC COLLISION. IT INCLUDED AN ALTERNATE LANDSCAPE PLAN WITH SOME VARIANCES TO OUR LANDSCAPE REQUIREMENTS, BUT IT INCLUDED ALL LANDSCAPE ELEMENTS, ALL THE REQUIRED TREES, KIND OF IN DIFFERENT LOCATIONS ON THE SITE DO DUE TO SOME ISSUES WITH UTILITIES AND EASEMENTS AND KIND OF IRREGULAR SHAPE OF THE PROPERTY, P AND Z RECOMMENDED APPROVAL OF THAT 5 TO 1. AND THEN THAT WENT TO THE APRIL 9TH TOWN COUNCIL MEETING WHERE TOWN COUNCIL APPROVED THAT SITE PLAN BECAUSE IT HAD VARIANCES WITH IT, AND THEY APPROVED IT AS PRESENTED 6 TO 1. THANK YOU. ANY QUESTIONS OR COMMENTS? NO THANK YOU. YOU'RE WELCOME. OKAY. NEXT IS A PUBLIC INPUT SECTION. IS THERE ANYONE PRESENT WHO WISHES TO ADDRESS THE COMMISSION ON A TOPIC THAT'S NOT ON OUR AGENDA? NO. 535

[00:05:11]

PUBLIC INPUT SESSION OPENED AND CLOSED. OKAY. OUR OUR FIRST ACTION ITEM IS TO CONSIDER

[4.A. Consider approval of minutes for March 24, 2026 ]

APPROVAL OF THE MINUTES FROM OUR LAST MEETING ON MARCH 24TH. IS THERE ANY ARE THERE ANY QUESTIONS OR DISCUSSION ABOUT THE MINUTES? EVERYONE HAD A CHANCE TO LOOK AT THEM. OKAY.

DO I HEAR A MOTION TO APPROVE? I'LL MAKE A MOTION TO APPROVE. IS THERE A SECOND? I'LL SECOND.

[4.A. VOTE]

OKAY, LET'S VOTE.

[4.B. Consider a recommendation on a Site Plan for Henry East, a proposed 248,000 square-foot industrial building on a proposed 24.46-acre lot to be platted in Henry East Addition, Lot 1, Block A, generally located on the south side of Whyte Road approximately 500 feet west of Cleveland-Gibbs Road - Case # 26-SP00003]

OKAY. MOTION CARRIES 5 TO 0. NEXT ACTION ITEM. CONSIDER A RECOMMENDATION ON A SITE PLAN FOR HENRY EAST. A PROPOSED 240 ZERO ZERO ZERO SQUARE FOOT INDUSTRIAL BUILDING ON A PROPOSED 24.46 ACRE LOT TO BE PLATTED IN HENRY EAST ADDITION LOT ONE, BLOCK A, GENERALLY LOCATED ON THE SOUTH SIDE OF WHITE ROAD, APPROXIMATELY 500FT WEST OF CLEVELAND GIBBS ROAD. CASE NUMBER 26 DASH SP THREE. THANK YOU CHAIRPERSON. THIS. WE'LL START OFF ON THE SITE PLANS WITH THE SMALL BUILDING HERE. THIS IS A SMALL 250 ZERO ZERO ZERO SQUARE FOOT BUILDING. SO THIS IS ON A JUST UNDER 25 ACRE SITE. ALSO IN THE AIRPORT AREA JUST WEST OF THE NORTHWEST REGIONAL AIRPORT. IT'S ON WILL BE ON THE SOUTH SIDE OF WHITE ROAD, APPROXIMATELY 500FT WEST OF CLEVELAND GIBBS ROAD. THE SITE WILL BE ACCESSED BY A PLANNED EXTENSION OF WHITE ROAD, WHICH WILL ULTIMATELY EXTEND FROM CLEVELAND GIBBS OVER TO SHOW YOU ON THE MAP HERE OVER TO 35 W. THE SITE IS JUST WEST OF THE NORTH LAKE RV STORAGE FACILITY. THE OWNER IS TRAMMELL CROW COMPANY ENGINEER BGE INCORPORATED. REPRESENTATIVES FROM BOTH OF THEM ARE HERE IF YOU HAVE ANY QUESTIONS FOR THEM. THE ZONING FOR THIS PROPERTY IS MIXED USE PLANNED DEVELOPMENT AND IT ALLOWS FOR USES SUCH AS OFFICE, WAREHOUSE AND DISTRIBUTION CENTER. IT'S A LITTLE BIT UNIQUE BECAUSE IT PROVIDES ANY SITE PLANS, BE PROCESSED LIKE A ZONING APPLICATION, AND MEET ALL NOTICE AND PUBLIC HEARING REQUIREMENTS OF THE UDC. SO THAT'S WHY YOU'LL NEED TO HOLD A PUBLIC HEARING ON THIS ITEM TONIGHT AND THEN APPROVE. SITE PLANS ARE CONSIDERED AN EXHIBIT TO THAT PLAN. DEVELOPMENT ORDINANCE. AGAIN, HERE'S THE THE SITE. NOW HERE'S THE SITE PLAN. THIS IS. ONE BUILDING JUST UNDER 250,000FT■!S. YOU'LL NOTICE IT'S BUILDING THREE BECAUSE JUST WEST OF THIS TRAMMELL CROW HAS ALREADY HAD SITE PLANS APPROVED FOR TWO BUILDINGS IN THAT AREA, AROUND 1,000,000.5FT■!S ALTOGETHER. THS SITE PLAN SHOWS THAT 248,000 SQUARE FOOT BUILDING, ALONG WITH 129 CAR PARKING SPACES AND 48 TRAILER PARKING SPACES, AND SOME FUTURE TRAILER PARKING SPACES. ALSO IDENTIFIED ALONG WITH THE SITE PLAN, LANDSCAPE PLAN AND SOME EXAMPLE BUILDING PHOTOS WERE PROVIDED IN LIEU OF BUILDING ELEVATIONS. BECAUSE THIS IS BEING PROVIDED A LITTLE BIT EARLIER ON IN THE PROCESS TO MAKE SURE THAT THEY HAVE THEIR ENTITLEMENTS THROUGH ZONING, ALLOWING THIS. SO THEY'RE COMMITTING TO THIS, THIS LEVEL OF, OF LOOK, THIS IS SIMILARLY HOW THE PROJECT TO THE WEST WAS APPROVED WITH SOME EXAMPLE RENDERINGS AND PHOTOS LIKE THESE. THIS IS FROM A PROJECT ACTUALLY IN NORTH FORT WORTH JUST SOUTH OF HERE. LIKE I MENTIONED, THIS. SITE PLAN, YOU HAVE TO HOLD A PUBLIC HEARING BEFORE CONSIDERING THIS BECAUSE THIS IS GOING THROUGH A SIMILAR PROCESS OF ZONING. YOU'LL MAKE A RECOMMENDATION ON IT TONIGHT. IT'LL GO TO TOWN COUNCIL. FOR FINAL APPROVAL. THIS SITE PLAN PACKAGE IS

[00:10:08]

ACCEPTABLE FOR CONSIDERATION. FOLLOWING THAT PUBLIC HEARING, WE RECOMMEND ONE CONDITION ON THIS. ANY ELEMENTS NOT INCLUDED IN THE SITE PLAN PACKAGE, SUCH AS, BUT NOT LIMITED TO THE FULL BUILDING ELEVATIONS, SIGNAGE AND LIGHTING SHALL MEET ALL APPLICABLE REQUIREMENTS OF THE UDC AT TIME OF PERMITTING. THIS WAS THE SAME CONDITION THAT WAS A PART OF THE APPROVAL FOR THE OTHER TRAMMELL CROW BUILDINGS. NOTICE OF THE PUBLIC HEARING WAS PROVIDED PER THE REQUIREMENTS OF THE UDC. NO WRITTEN COMMENTS HAVE BEEN RECEIVED. SO AFTER HOLDING A PUBLIC HEARING, YOU CAN CONSIDER A RECOMMENDATION ON THIS SITE PLAN. OKAY, OKAY.

ANYBODY HAVE QUESTIONS FOR ME? OKAY, I'VE GOT SOME QUESTIONS, IF I MAY. OH, SORRY. GO AHEAD PLEASE. OKAY. FIRST, IT'S 540. WE WILL OPEN THE FLOOR FOR PUBLIC HEARING. IS THERE ANYONE PRESENT WHO WOULD LIKE TO ADDRESS THE COMMISSION ON THIS SUBJECT? NO. 541 WILL CLOSE THE HEARING THEN. OKAY. I'M GOING TO ASK YOUR QUESTIONS. YES, MA'AM. YOU KNOW, I FEEL LIKE WE'VE APPROVED QUITE A FEW OF THESE TYPES OF WAREHOUSE IN THIS AREA, WHICH I THINK IS IMPORTANT TO THE TOWN'S DEVELOPMENT. BUT CAN WE CONTINUE TO SUSTAIN THE REQUISITE ENERGY? YOU KNOW, I DON'T DO WE KNOW WHAT WATER OR ELECTRIC USE IS GOING TO BE REQUIRED? AND CAN WE SUPPORT THIS AS A TOWN? AND WHAT ARE THE RAMIFICATIONS FOR THE RESIDENTS ON THE INDUSTRIAL BUILD UP ON THIS AREA? DO WE HAVE ANY INSIGHTS INTO THAT? SO THIS PARTICULAR LOCATION IN OUR COMPREHENSIVE PLAN AND ALSO ZONING CALLS FOR THIS USE. AND BASED ON OUR COMPREHENSIVE PLAN, WE HAVE MASTER PLANS FOR WATER AND SEWER AND ROADWAYS TO HANDLE WHAT WHAT THIS TYPE OF DEVELOPMENT WOULD NEED. SO FOR SPECIFIC USES PLANNED IN IT AND POSSIBILITIES, MAYBE APPROPRIATE TO HAVE A REPRESENTATIVE OF THE DEVELOPER TO SPEAK TO SOME OF THOSE POSSIBILITIES? THAT'D BE GREAT. THANK YOU. SURE. HI, MR. KELLOGG AT TRAMMELL CROW COMPANY. SO THANKS FOR HAVING US TODAY. WE BUILD THESE BUILDINGS SPECULATIVELY SO WE DO NOT HAVE TENANTS IN TOW. WHEN WE BREAK GROUND ON THEM.

HOWEVER, WE DO PROJECTS WITH SOME OF THE LARGEST E-COMMERCE DISTRIBUTION MANUFACTURING COMPANIES IN THE US. OUR PROJECT SOUTH OF HERE AT 35 EAGLE, IS A 6,000,000 SQUARE FOOT MASTER PLAN DEVELOPMENT. WE HAVE BUILDINGS WITH AMAZON, BUT WE HAVE BUILDINGS WITH TONS OF EXCELLENT TENANTS. AND SO WE DON'T NECESSARILY KNOW WHO'S GOING TO OCCUPY THESE BUILDINGS.

BUT I WILL SAY THEY TYPICALLY BRING JOBS. THEY BRING A TAX BASE FOR THE TOWN OF NORTH LAKE.

AND AS NATHAN SAID, THEY MATCH THE TOWN'S MASTER PLAN. WE'RE ALSO EXTENDING UTILITIES TO THIS AREA AS PART OF OUR DEVELOPMENT AGREEMENT WITH THE TOWN WATER LINES IN CLEVELAND GIBBS ROAD, A WATER LINE IN WHITE ROAD. AND WE'RE ACTUALLY CONSTRUCTING WE'RE PLANNING ON CONSTRUCTING ON WHITE ROAD AS PART OF OUR DEVELOPMENT WITH THE TOWN OF NORTH LAKE, WHICH IS ON YOUR FUTURE THOROUGHFARE PLAN. SO THANK YOU. ANY OTHER QUESTIONS OR DISCUSSION? SORRY IF I MAY. ONE MORE QUESTION. ARE WE LOOKING TO INCORPORATE ALTERNATIVE SOURCES OF ENERGY? YOU KNOW, WITH LARGE SCALE BUILDINGS LIKE THIS? IS SOLAR POSSIBILITY THAT JUST TO HELP, YOU KNOW, MINIMIZE THE IMPACT ON THE TOWN? AND ARE THERE ALTERNATIVE WAYS THAT WE CAN POWER THIS BUILDING, GET YOU TENANTS, BUT ALSO NOT DROWN DRAWN THE ENERGY USE OF THE TOWN? SURE. YEAH. GREAT QUESTION. SO IN TEXAS, OUR POWER IS RELATIVELY AFFORDABLE.

SO ON THE COAST YOU'RE SEEING MORE SOLAR ON ROOFS OF INDUSTRIAL WAREHOUSES. I THINK IN OUR EXPERIENCE HERE, IT DOESN'T QUITE MAKE SENSE. IN TEXAS, PARTICULARLY TEXAS DOESN'T OFFER NET METERING. WE HAVE DONE SOLAR ON OTHER PROJECTS IN UNIQUE CIRCUMSTANCES ON THE COASTS, AND WE'VE EXPLORED IT HERE. BUT THE POWER AVAILABILITY IN TEXAS AND THE RELIABILITY OF THE GRID IS JUST SUPERIOR TO SOLAR. SO THERE ARE NO ISSUES WITH WE HAVE NOT HAD ISSUES POWERING OUR BUILDINGS. AND, YOU KNOW, THERE ARE WE'RE WORKING AND WE HAVE WELL SERVE LETTERS FROM THE EXISTING UTILITY PROVIDERS IN THE AREA. THANK YOU. HANG ON.

MAYBE JUST A FOLLOW UP TO THE FIRST LINE OF QUESTIONING. DOES THE MASTER PLAN TAKE INTO CONSIDERATION THROUGHPUT OF TRAFFIC BASED ON WHAT YOU ULTIMATELY END UP PUTTING IN THERE, AND WHETHER OR NOT THAT'S HEAVY TRUCK OR, YOU KNOW, YOU'VE GOT X NUMBER OF PARKING

[00:15:06]

SPOTS? WE ALL KNOW THE SITUATION WITH TRAFFIC UP HERE. IS THAT FACTORED INTO ALL THIS? YES. OUR THOROUGHFARE PLAN TAKES INTO ACCOUNT THESE USES. ACTUALLY, WHITE ROAD IS A SPECIFIC TYPE OF THOROUGHFARE THAT WE JUST USE IN OUR INDUSTRIAL AREAS. AND AND THEY WILL BE BUILDING IT OUT AND EXTENDING IT OUT TO WHERE THE 35 W FRONTAGE ROAD WILL BE.

OKAY. OKAY. THANK YOU, THANK YOU. ANY OTHER COMMENTS OR QUESTIONS? ANOTHER THING I, I FAILED TO MENTION ON THIS ORIGINALLY THIS SITE WAS PLANNED FOR RV PARK. SO I THINK THIS REALLY FITS IN A LOT BETTER WITH, WITH WHAT'S IN THE AREA AND WHAT'S PLANNED IN THE AREA. SO OKAY. ALL RIGHT. DO I HEAR A MOTION? I MAKE A MOTION TO APPROVE SITE PLAN FOR HENRY EAST TO PROPOSE 248,000 SQUARE FOOT INDUSTRIAL BUILDING ON A PROPOSED 24.46 LOT TO BE PLATTED IN THE HENRY EAST ADDITION LOT ONE, BLOCK A, GENERALLY LOCATED IN THE SOUTH SIDE OF WHITE ROAD, APPROXIMATELY 500FT WEST OF CLEVELAND GIBBS ROAD. CASE NUMBER 26-SP00003 WITH THE. LET'S SEE RIGHT HERE. ELEMENTS NOT INCLUDED IN THE SITE PLAN PACKAGE, SUCH AS. BUT NOT LIMITED TO BUILDING ELEVATION. SIGNAGE AND LIGHTING SHALL MEET ALL APPLICABLE REQUIREMENTS OF THE UDC AT THE TIME OF PERMITTING. OKAY. THANK YOU. DO

[4.B. VOTE]

I HEAR A SECOND? SECOND LOVE? MOTION CARRIES UNANIMOUSLY. ALL RIGHT. OKAY. NEXT ITEM ON THE

[4.C. Consider approval of a Site Plan for Project 10X, a proposed 4-building industrial campus on a 120.005-acre tract of land to be platted as Alliance Northport West Addition, Lot 5, Block A, generally located west side of Harmonson Road and approximately 1,600 feet east of FM 156 - Case # 26-SP00002]

AGENDA. CONSIDER APPROVAL OF A SITE PLAN FOR PROJECT TEN X, A PROPOSED FOR BUILDING INDUSTRIAL CAMPUS ON A 120 .005 ACRE TRACT OF LAND TO BE PLOTTED AS ALLIANCE NORTH PORT WEST ADDITION LOT FIVE BLOCK A GENERALLY LOCATED WEST SIDE OF HARMANSON ROAD AND APPROXIMATELY 1600FT EAST OF FM 156. CASE NUMBER 26-SP2. ALL RIGHT. SO. THAT LAST SITE PLAN WAS JUST 250,000FT■!S. BUT YOU ADD THAT WITH THE OTHER TWO BUILDINGS. TRAMMELL CROW PLANNING IS ABOUT 1.8 MILLION. THIS ONE PROJECT TEN X. THIS IS THE MP MATERIALS PROJECT.

THEY'RE PLANNING TO BUILD ABOUT THE SAME AMOUNT OF BUILDING SPACE FOR THEIR PROJECTS. IT'S OVER 120 ACRES. THIS AREA IS NORTH OF THE SPEEDWAY ON THE WEST SIDE OF CURRENT HARMON ROAD ALIGNMENT. IT WILL BE USED KIND OF DURING CONSTRUCTION TO ACCESS THE SITE. AND HERE, HERE'S A LOOK AT WHERE THAT SITE IS ON THE EASTERN BOUNDARY OF THE SITE IS WHERE A NEW NORTH SOUTH THOROUGHFARE WILL BE CONSTRUCTED, MATCHING OUR MASTER THOROUGHFARE PLAN. THIS WILL EXTEND DOWN TO VICTORY CIRCLE ON THE NORTH SIDE OF THE SPEEDWAY, AND THEN THIS WILL CONTINUE UP NORTH TO ULTIMATELY TO FM 1171 AND AND PAST THAT. LIKE I SAID, THIS IS THE MP MATERIALS PROJECT. MP TEN X DEVELOPMENT IS THE OWNER. THE APPLICANT DEVELOPER IS HILLWOOD CONSTRUCTION SERVICES. WESTWOOD PROFESSIONAL SERVICES IS THE ENGINEER. AND THE ZONING FOR THIS IS INDUSTRIAL PLAN DEVELOPMENT.

ON. ALL RIGHT. SO HERE'S A LOOK AT THE SITE PLAN FOR THE FACILITY. IT ACTUALLY

[00:20:10]

THEY PLAN FOR BUILDINGS ON THIS WITH ONE BUILDING BEING THE THE LARGEST AT JUST UNDER ONE POINT 7,000,000FT■!S OR, OR ALL THE BUILDINGS TOTALED OR ONE POINT 7,000,000FT■!S, OVER 1800 PARKIG SPACES PLANNED AND INCLUDING 30 ACCESSIBLE PARKING SPACES ALONG WITH THE SITE PLAN, LANDSCAPE PLANS AND BUILDING ELEVATIONS WERE PROVIDED. HERE'S A LOOK AT KIND OF THE OVERALL PLANTING PLAN. THERE ARE SEVERAL PAGES. THIS IS SUCH A LARGE SITE. THEY'RE ADDING LOTS OF OF LANDSCAPING ELEMENTS. SO I INCLUDED THIS CHART IN HERE TO KIND OF SHOW YOU THE NUMBER OF TREES TOTAL THAT THEY'RE, THEY'RE PLANTING AND THE AMOUNT OF SQUARE FOOTAGE OF LANDSCAPE AREA. AND THEY'VE INCLUDED BUILDING ELEVATIONS FOR ALL THESE BUILDINGS. THIS IS A RENDERING THAT THEY PROVIDED FOR, FOR THEIR MAIN BUILDING. ALL OF THESE PLANS MEET ALL REQUIREMENTS OF THE INDUSTRIAL PLAN, DEVELOPMENT, ZONING, AND ALL APPLICABLE REQUIREMENTS OF THE UNIFIED DEVELOPMENT CODE. AND SINCE THIS IS A TYPICAL SITE PLAN, WE'RE NOT HAVING TO HOLD A PUBLIC HEARING ON IT. AND YOU HAVE THE ABILITY TO APPROVE THAT TONIGHT. AND SINCE THEY ARE NOT REQUESTING ANY VARIANCES, IT DOESN'T HAVE TO GO ON TO TOWN COUNCIL. AND I WILL POINT OUT THERE ARE SEVERAL PEOPLE ASSOCIATED WITH THIS PROJECT HERE. IF YOU HAVE ANY QUESTIONS FOR THEM OR IF THEY WOULD LIKE TO COME UP AND SPEAK ANY MORE ABOUT THE PROJECT. OKAY. ANYONE HAVE QUESTIONS OR COMMENTS? I'M MORE OF A SIMPLE QUESTION, BUT I LOOK AT THIS BUILDING THAT YOU JUST HAD UP, JUST LIKE THE ONE THAT TRAMMELL CROW HAD PROPOSED.

AND IF WE'RE GOING TO BE INDUSTRIAL, IT'S GREAT THAT IT HAS THE ESTHETICS THAT IT DOES.

WHAT ARE THE CONTROL MECHANISMS TO MAKE SURE THAT WE'RE WE'RE LOOKING AT TODAY DON'T DEVIATE.

AND THAT ENDS UP LOOKING LIKE A VERY INDUSTRIAL BUILDING AS OPPOSED TO THE VERY NICE GLASS, YOU KNOW, FRONT DESIGN, ETC. SO THE, THEY'RE COMMITTING TO BUILDING THIS BY HAVING IT IN THE, THE SITE PLAN. ANY CHANGES TO WHAT ARE INCLUDED IN THE SITE PLAN WOULD HAVE TO COME BACK BEFORE YOU AND GET APPROVAL. I HAVE A QUESTION. DO WE HAVE THE INFRASTRUCTURE TO SUPPORT THIS TYPE OF MANUFACTURING? YOU KNOW, THINKING ABOUT OUR FIRST RESPONDERS, IS OUR TOWN EQUIPPED TO SUPPORT THIS TYPE OF INDUSTRY IN THE TOWN? YES, WE BELIEVE SO. AND, YOU KNOW, WE'RE IN OUR EARLY IN THE DEVELOPMENT PROCESS, BUT WE'VE I THINK WE'VE GOT A REPRESENTATIVE FROM OUR EMERGENCY SERVICES DISTRICT HERE, AND THEY'LL BE HEAVILY INVOLVED IN THAT TO AND MAKE SURE IT MEETS ALL OF THE CODES AND. AND SO THAT WE'RE ABLE TO HANDLE ANY ISSUES THAT ARISE. SIMILARLY, THIS WHOLE AREA NORTH OF THE SPEEDWAY WAS DESIGNED FOR. IT WAS PLANNED FOR THESE TYPE OF USES. AND SO WE'VE GOT WATER, SEWER MASTER PLANS, MASTER THOROUGHFARE PLAN, ALL TO HELP SERVE DEVELOPMENTS LIKE THIS. ALSO, A THING THAT WE'RE BENEFITING FROM IT WAS A ROUGH TO GO THROUGH IS THAT ENCORE TRANSMISSION LINE THAT WAS IN PLACE. IT'S JUST NORTH OF THIS SITE. AND BECAUSE OF THAT, A SUBSTATION WILL BE ABLE TO BE BUILT OFF OF THAT. THAT WILL PROVIDE PLENTY OF POWER FOR THIS DEVELOPMENT AND THE SURROUNDING DEVELOPMENT TO COME. AND AND WHAT COST IS THAT COMING? IS THAT COMING FROM TAXPAYERS OR WHO'S PAYING FOR THIS? THAT'S THE ENCORE. THE ELECTRIC DELIVERY PROVIDER. THEY WILL PROVIDE THAT PAYMENT. IT'S IT'S ALREADY BEEN CONSTRUCTED. OKAY. GOTCHA. OKAY. DO WE NEED ANY OTHER ADDITIONAL EMS SERVICES LOCATION FOR THIS TYPE OF INDUSTRY? THERE ACTUALLY IS A FIRE STATION CURRENTLY UNDER CONSTRUCTION, NEARING COMPLETION DOWN IN THE SOUTHERN PART OF TOWN. AND PART OF THE NEED FOR THAT WAS TO HELP SERVE THIS AREA BETTER. YEAH. OTHER QUESTIONS? THANK YOU. ANYBODY ELSE? NO. DO I

[00:25:10]

HEAR A MOTION? MOVE TO APPROVE? YOU MOVE TO APPROVE AS SUBMITTED. YES. IS THERE A

[4.C. VOTE]

SECOND? SECOND. THE VOTE. MOTION CARRIES UNANIMOUSLY. OKAY. THAT WAS THE LAST ITEM ON OUR AGENDA. I WANT TO THANK ALL THE REPRESENTATIVES FOR COMING AND BEING AVAILABLE TO ANSWER OUR QUESTIONS. EVERYTHING SEEMED TO TO GO PRETTY WELL WITHOUT HAVING TO BOTHER YOU TOO MUCH. BUT THANK YOU FOR BEING HERE. WE REALLY APPRECIATE IT. THANK YOU EVERYONE. AND IT IS

* This transcript was compiled from uncorrected Closed Captioning.